Decision rights
Who decides what in the Nexus programme: the division of accountability between GCRI, GRF, GRA, national structures and competent authorities, the Nexus Universe gates, and the twenty-nine decisions o
Where this fits. Governance in operation › all levels · all six pillars · GCRI, GRF, GRA, national structures, Nexus Standards bodies and competent authorities · gates G0 to G7 · canonical page.
In brief
Every decision in the programme has one accountable decider, and that decider is on the record. Three registers set out who decides:
the division of accountability between the institutions, the national structures and the competent authorities, published on the GCRI and GRF sites;
the gates of the programme year, G0 to G7, which GRF records as steward of Nexus Universe;
the decision-rights matrix of the Nexus Standards, DR-01 to DR-29, which is proposed.
Boundary. Public, regulatory, fiduciary and operational decisions are never taken inside the programme. "Decisions and execution remain with the relevant government, operator or licensed institution" (National Nexus). The competent authority stands outside the programme. "The authority decides; the programme informs."
The division of accountability
The Nexus Consortium model, as published on How Nexus Consortium works, sets one accountable party for each function:
Integrated consortium secretariat
GCRI Canada within the approved lead mandate
GRF, GRA, national and regional structures
One coordinated programme with separate institutional responsibilities.
Evidence, methods and technical assistance
GCRI technical and evidence stewardship
Researchers, domain experts, national source authorities
Problems become testable questions and reusable capability.
Leadership, convening and Universe governance
GRF within its instruments
GCRI technical office, GRA readiness interface, hosts, national delegates
Year-round participation culminates in structured annual work.
Finance, insurance and development readiness
GRA
Competent financial institutions, supervisors, public finance, domain teams
Risk evidence becomes useful diligence material, not an approval or a transaction.
National agenda and local participation
Competent National Nexus structures
National institutions, leaders, working groups, communities, authorities
National ownership precedes federation.
Scientific and editorial acceptance
Qualified, conflict-managed reviewers and the publisher
Source owners, country reviewers, independent experts
Institutional influence cannot decide a scientific conclusion.
Official decisions and execution
The relevant government, operator or licensed institution
Bounded Nexus interfaces where agreed
Nexus prepares evidence and supports lawful continuation.
Each institution states its own boundary. GCRI "does not regulate, certify, license or approve". GRF "does not regulate, finance, procure or certify". GRA "does not lend, underwrite, rate, invest, advise on or arrange transactions. Readiness is not approval" (GCRI, GRF and GRA). The same division appears on Board and governance, GRF in the Consortium and the Consortium finance interface.
The gates of the programme year
GRF, as steward of Nexus Universe, holds four kinds of decision: the mandate (G0), admission (G1), gate decisions, and publication (G6). It holds them "modelled on exercise direction", separate from the controllers and evaluators of an exercise (Programme governance). This follows the separation of exercise direction, control and evaluation in established exercise practice, which GRF cites from the WHO Simulation Exercise Manual.
G0
Annual programme authorised
Planning, Q1
G1
Missions admitted
Readiness preparation, Q2
G2
Data and resources qualified
Readiness preparation, Q2
G3
Build accepted for exercise
Controlled build, Q2
G4
Controlled live operation authorised
Action Week, Q3
G5
Evidence sealed and stand-down recorded
Closeout, Q3
G6
Publication authorised
Reporting, Q4
G7
Renewal reviewed
Renewal, Q4
"A cycle gate is a programme decision. It is not a public-authority approval, a certification or a deployment authorisation." The phases and handoffs around each gate are in The programme year.
The Nexus Standards decision rights
The proposed working model of the Nexus Standards has one formula: "Councils decide; working groups draft; everything else is open. Global councils decide global matters, national councils decide national matters, and neither decides for the other." Its matrix gives each of twenty-nine decisions exactly one decider.
Five invariants hold across the matrix:
Each decision has exactly one decider.
The Global Standards Council has no say on a national decision.
No national body decides a global adoption.
The National Leadership Council never decides adoption, technical content or conformance.
Technology-support parties hold no right beyond any person's. A single technology-support liaison attends open sessions without a vote or a chair.
Who decides at each stage of a standard. Each stage of a standard has its own decider:
the technical committees accept work items (DR-02), move drafts into review (DR-06) and set the stage after last call (DR-07) and the candidate stage (DR-08);
the working groups decide the content of their drafts (DR-04), and the editors dispose of comments (DR-05);
the Global Standards Council adopts a standard after a 90-day last call by two thirds of all voting members, with no unresolved national objection or a recorded override (DR-09).
Two independent implementations and published test vectors must exist before adoption. National adoption then belongs to each National Standards Council (DR-20 to DR-25).
Appeals. A technical appeal goes from the working-group co-chairs to the technical committee, then to a Technical Management Division (DR-26), then to the Global Standards Council on the record. A process appeal goes to the Ethics, Conflicts and Appeals Panel (DR-27). It is filed within thirty days, acknowledged within five and decided within sixty.
The standards gates G1 to G7 of the working model (work item accepted, draft ready, ready for last call, last call closed, implementation evidence, adoption, systematic review) are different from the gates G0 to G7 of the programme year. They share numbers only.
Why decision rights are written this way
When interdependent risks cross institutional boundaries, accountability fails at the seams between institutions. That is the point the OECD Recommendation on the Governance of Critical Risks addresses when it calls for clear roles and responsibilities across government and operators (OECD, 2014). The separation of evidence, deliberation and allocation, and the single decider per decision, keep each claim attributable. A modelled estimate cannot appear as consensus, and a dialogue outcome cannot appear as investment readiness (Nexus Consortium relationship).
Sources
OECD (2014). Recommendation of the Council on the Governance of Critical Risks. OECD/LEGAL/0405. legalinstruments.oecd.org
GCRI: Board and governance; National Nexus.
Nexus Standards: Governance. Governance register, working model and decision-rights matrix (PROPOSED; proposal NXS-STD-PC-000008).